5/6-8/08 I went up to the property for 3 days: Tuesday through Thursday.
I arrived at 11:50 to a pleasant 56 degrees. I brought a bundle of 3/4" EMT with me and after moving in and having lunch, I carried it up to the cabin. Then I went to work in the loft and installed the 6th and 7th receptacle boxes and the EMT between them.
I called L&I and scheduled the inspection and I called Mike Dickinson and scheduled the dig. The schedule now stands as:
Mon 5/12 - I will buy phone jack equipment at Home Depot
Wed 5/14 - I will install at least the bedroom phone jack
Fri 5/16 - Call 1-800-424-5555 to schedule location of buried utilities before digging
Wed 5/21 - Mike will dig the lower trench and plant the pole
Wed 5/21 - I will schedule Mike for closing the trench on 5/28
Wed 5/21 - I will Call 509-548-7761 and request power disconnect on 5/22
Thu 5/22 AM - PUD will disconnect the power at the transformer
Thu 5/22 - I will glue up and lay out the fiber optic conduit and install the hand hole
Thu 5/22 - I will string out the phone wire
Sat 5/24 - Brian Kemly and I will install the conduit, meter base and wire
Tue 5/27 PM - Verizon will inspect the trench and hook up phone service to the cabin
Tue 5/27 PM - L&I will inspect the installation of service and of the loft baseboard EMT
Tue 5/27 PM - PUD will energize the meter base and service panel
Tue 5/27 PM - I will energize a baseboard outlet circuit and maybe some others
Wed 5/28 - Mike will close the lower portion of the trench
Wed 5/28 - I will close the upper portion of the trench and build vault forms
Later, as weather and time permit, I will mix and pour concrete into the vault forms.
After all the phone calls, I went up and finished installing the 8th, and last, receptacle box and EMT in the loft baseboard. I also installed the box for the utility room switches. This box will also be a junction box for several wires so it is extra deep.
Just as I finished lunch, Earl stopped by for a visit. We went up to the cabin and had a nice visit. I took a couple pictures of him and me. After he left, I wired up the feed wire from the utility room switch box to the string of loft baseboard receptacles. I specifically want to get this inspected soon because it runs up the corner of the loft where I plan to run other wires. If there is a problem with this plan, I want to learn about it as early as possible.
With the electrical work pretty much done, that I want to get inspected right away, I turned to my next priority. I want to get a wheelchair accessible ramp up to the cabin done as soon as possible. The weather is great for visiting right now and I want to get Herb and Marie Roberts up for a visit soon.
I made two hangers out of 16 gauge steel strap and used them to mount the two 6x6s, the boys had dragged over, onto the edge of the back deck. Then I dragged two more long 6x6s up from where they had been stored down by the trailer. These four timbers will be the main supports for the ramp.
I took a picture of the ramp under construction.
Bert and Ernie spotted my pickup coming back to the property so they were all over me for dog biscuits as I parked and carried the conduit up to the cabin. They both were extra clean with shiny coats. It looked like they had just had a bath. We did a lot of hugging in between biscuits and trips up the hill.
Next I went back to work on the ramp. I dug holes in the snow where footings for the cross beams need to go and placed a bunch of rocks in the holes as the beginnings of the footings. I also cleared away most of the brush that was growing in the way of the ramp. Most of the brush had stem diameters of about a half inch or less so I broke most of them off just with my hands. I used an axe on the bigger ones. The brush had thorns on it so I had to be a little careful in getting it out. But I did get a nice clear right-of-way for the ramp. My back was pretty sore, though, probably from leaning over to pick up the rocks. It will heal. I went in, had lunch, and left for home at 1:35.
©2008 Paul R. Martin, All rights reserved.